Explore this system
Step through curated paths without changing the source diagram.
Beat
Next
ReadyChapter 01 / 01
Guided chapter
Diagram guideExplore this system
Inspecting compiled semantics
E ExportT ThemeS Style0 Reset+ Zoom in- Zoom outEsc Close
Find a node
⌕/
No matching nodes
Semantic passport
Verified source
Authored reach
Route probeChoose a start node
Pick two semantic nodes on the diagram
Choose the source, then the destination. Direction matters.
Semantic lensCompare system roles
Choose up to two semantic kinds. One reveals its real traffic; two compare only direct authored relationships.
Choose a kind to inspect its nodes and touching relationships.
Semantic radar
Building overview
Click nodeDrag to pan
Semantic radar needs more MAP space.
Two Kinds of Frequency
• Time-based: Frequency plus Units (DAYS, WEEKS, MONTHS, YEARS); fixed schedules count from the target date, floating from the last work order's start date
• Meter-based: Units to Go = Next Meter Reading − Life To Date − Generate WO Ahead By
Generation Rules
• Generate Work Orders runs from the PM application action or the PMWoGenCronTask
• The PM must be ACTIVE and the asset or location OPERATING; a floating PM that is not due raises BMXAA3191E "PM is not due yet"
What the Work Order Inherits
• Job Plan Sequence uses the Counter to choose which job plan applies this time
• Work Type, Priority, Owner / Owner Group and GL account copy from the PM, then the Asset, then the Location