All learning series · Manage capability · Part 1
Planning and Scheduling
Build a feasible work plan before trying to optimize it.
Start here
Confirm this product is ready, then use the lesson. The readiness checks are the gate for configuration, for a first journey and for production.
- Are you ready to use Planning and Scheduling? Licensing and AppPoints, the records that must exist, and three checklists.
- Basics
- Configuration
- Practical example
- Practice and verify
- Advanced concepts
Are you ready to use Planning and Scheduling?
Confirm the calendar, the shifts and the people who can do the work before you build a schedule. Planning and Scheduling is part of Maximo Manage. Optimizer is a separate installation and is not required for a manual Gantt.
Before configuration
You need a Manage organization and site, a security group that can open the scheduling applications, and a decision about which calendar the schedule will use. Limited access excludes Planning and Scheduling from the three modules a Limited user may choose.
Before the first successful journey
The work list needs one calendar, at least one shift whose work periods cover the dates on the list, and work orders whose scheduled dates fall inside that window. Labor or crews need the same calendar and shift, unless you deliberately use alternate resource availability.
Before production use
Extend work periods through the longest horizon planners will move, agree who owns the calendar, and decide whether optimization will run. Optimization needs the Optimizer installation and its own AppPoints. A working manual schedule does not include that install.
Licensing, entitlement and AppPoints
Planning and Scheduling is entitled and installed as part of Maximo Manage. The MAS 9.2 licensing guidance prices it at the Base tier, or at the Premium tier when the same person is also given an industry-solution or add-on application. It is not a separate install line on the AppPoints install table. A Limited user can use three Manage modules and can update work orders, and those three modules exclude Planning and Scheduling, Application Administration, Administration, Integration, System Configuration and Security.
Keep four facts separate for Planning and Scheduling. Entitlement is the proof of entitlement and the License Information for IBM Maximo Application Suite. The MAS 9.2 licensing guidance supplements that agreement. Available AppPoints are the pool shown on the AppPoints Usage dashboard: Suite administration, then Suite, then Administration, then AppPoints Usage. Assigned access is the security group together with the user type on the person: Limited, Base or Premium, and Authorized or Concurrent. Consumption is what that assignment draws. Authorized users and administrators reserve AppPoints continuously. Concurrent users draw AppPoints while they are signed in. Install AppPoints stay reserved for the life of that environment. A non-production install of a component draws no install AppPoints when the same component is already installed in production. Administrators and User Management users open the dashboard. Other people need the LICENSEUSAGE security group. Compliance enforcement and idle timeout sit on the dashboard Configuration tab and are suite-administrator settings.
The same guidance publishes these user conversion ratios: Limited is 5 AppPoints for one concurrent user and 2 for one authorized user; Base is 10 concurrent and 3 authorized; Premium is 15 concurrent and 5 authorized; an administrative Base user is 10 AppPoints and an administrative Premium user is 15, both as authorized users. A Base administrator who already reserves 10 AppPoints can be given Premium application access with no further AppPoints. Those ratios were read from the MAS 9.2 licensing guidance on 18 October 2026. Your agreement sets how many AppPoints you purchased. An application that opens shows that the component is deployed. Read the proof of entitlement and the dashboard as well.
Installed and enabled applications
The scheduling applications ship with Manage. Confirm Graphical Scheduling, Graphical Assignment and Graphical Work Week open for a planner. Confirm the Manage build on the workspace. Optimizer, if you will use it, is a separate catalog deployment. A schedule that only uses the Gantt does not require that deployment.
Foundation configuration
The calendar that matters is the calendar you name on the work list or schedule. Graphical Work Week asks for Calendar and Shift, and those two fields are the availability the Gantt uses. The work-list start and end dates control which work periods appear. Include an extra week beyond the week you intend to plan so work can move. Work with no scheduled dates stays off the Gantt unless you select Include Work Orders Without Dates, which writes a scheduled start on the work order.
Shifts create the working hours. Define the shift pattern in the Calendars application and apply the shifts so the calendar has work periods. A resource list allows up to five shifts. If Restrict Resource Availability is empty, the chart includes every labor and crew on that calendar and those shifts. Show Labor and Show Crews choose which of those records are drawn.
Labor availability is the calendar and shift on the labor record. Crew availability is the calendar and shift on the crew. The craft or crew type on the job plan or work plan has to match a person or crew or the requirement has nobody to cover it. Qualifications and skills matter when the journey assigns by skill rather than by a named person. Alternate resource availability is the path for capacity that is not a labor or crew record. It does not remove the calendar and shift from the work list.
The site time zone is the clock for the horizon. Compare the site time zone with the hours on the calendar work periods before you call a person available at 17:00. Non-working days and exceptions are the gaps in those work periods. If the horizon runs past the last work period, that part of the Gantt has no capacity.
When a work order sits outside the work-list dates, Graphical Work Week leaves it off the graphical view. When a person or crew has no work period in the window, they contribute no hours there. Check capacity in Graphical Resource View for the same calendar and shifts. Optimizer is a different product: its models read this same availability, and they also need the Optimizer installation.
Product configuration
Create the work list or schedule in the application you will actually use. Graphical Work Week is the short-horizon assignment list. Graphical Scheduling is the longer plan. Name the calendar, the shift, the date window and a work query. Restrict resources by craft, labor, crew or crew type when the whole organization should not appear. Rolling schedule is optional and refreshes the list on an interval you set. Review the default of including every resource on the calendar before you publish a schedule to a large site.
Infrastructure and integration
A manual schedule runs inside Manage. No extra route, queue or map service is required for the Gantt. Dispatch and spatial scheduling add a map provider, a geolocation on the work, and start and end locations on labor or crews. Those belong to the Optimizer spatial model and to dispatch, not to every schedule. Optimization jobs need the Optimizer service deployed and reachable from Manage.
Data and operational readiness
The first journey needs three work orders in the same site, each with a duration, a target or scheduled start inside the work-list dates, and a craft or crew requirement that matches a labor or crew record. Give that labor or crew the same calendar and shift, and enough work periods to cover the duration. One predecessor between two of the work orders is enough to see a dependency. The planner who runs the journey needs a security group for the scheduling application and for the work orders.
Setup order for a schedule
- 1. Organization, site and time zone The site clock is the horizon the work-list dates use.
- 2. Calendar, shifts and work periods Apply shifts so work periods extend through the planning window.
- 3. Crafts, skills, labor and crews Put the same calendar and shift on the people and crews the work requires.
- 4. Work with dates, duration and a matching craft Scheduled dates must sit inside the work-list start and end.
- 5. Work list or schedule Name that calendar and shift. Restrict the resource query to the crew you mean.
- 6. Optimizer, only for an optimization model A separate install. Resource leveling, capacity planning, maintenance scheduling, assignment and spatial scheduling are models, not part of the Manage entitlement.
| Requirement | Why needed | Mandatory/Conditional/Optional | Where to configure or verify | Minimum working example | Verification procedure | Consequence if missing | Remediation | Source |
|---|---|---|---|---|---|---|---|---|
| Manage entitlement at Base, or Premium if this person also has an industry solution or add-on | Planning and Scheduling is included with Manage and is outside the three modules a Limited user may choose. | Mandatory | Suite administration → Suite → Administration → AppPoints Usage. Manage → Security → Security Groups, and the user type on the suite user. | A planner as an authorized Base user, or a Premium user when the same groups include an industry application. | Open AppPoints Usage, find the planner, and read the tier next to Planning and Scheduling access. | The planner signs in and the scheduling applications stay out of the security group. | Move the user to Base, or to Premium when industry access is also granted. Confirm the group includes the scheduling applications. | Licensing in Maximo Application Suite 9.2 |
| One calendar named on the work list, with work periods through the horizon | Graphical Work Week uses the calendar on the work list as the availability calendar. | Mandatory | Calendars application, then the Calendar field on the work list. | Calendar DAY, work periods generated for the next six weeks. | Open the calendar and confirm work periods exist on every day you will show on the Gantt. | Dates past the last work period show no capacity. | Apply shifts again out to the end of the horizon planners will use. | Creating work lists in Graphical Work Week |
| At least one shift on that calendar | The shift supplies the working hours. A resource list allows up to five shifts. | Mandatory | Calendars → Shifts, then the Shift field on the work list or resource list. | Shift DAY, 07:00–15:30, applied to calendar DAY. | Create a resource list for DAY and DAY and read the hours on the chart. | The chart has a calendar and no working hours, so nobody is available. | Define the shift pattern and use Apply Shifts so the work periods match the pattern. | Creating resource lists |
| Labor on the same calendar and shift, or alternate resource availability | Assignment uses the labor calendar unless you choose alternate availability for capacity that is not a person record. | Conditional | Labor application, Calendar and Shift. Alternate availability on the schedule when you are not assigning named people. | Labor ELEC-1 on DAY / DAY, craft ELEC. | In Graphical Resource View, Show Labor, and confirm ELEC-1 appears under that shift. | The craft requirement has no person, or the person appears with zero hours. | Set the labor calendar and shift, or define alternate availability and leave named labor out of this journey. | Creating resource lists |
| Crews on the same calendar and shift when the work plan uses a crew | Crew availability is the crew calendar, not the calendars of the members alone. | Conditional | Crews application, Calendar and Shift. Crew type on the work plan. | Crew ELEC-CREW, crew type ELEC, calendar DAY, shift DAY. | Show Crews on the resource list and confirm the crew hours match the shift. | Crew work sits unassigned because the crew has no work period in the window. | Set the crew calendar and shift, and match the crew type to the work plan. | Creating resource lists |
| Craft, skill or qualification that matches the work plan | The schedule can only offer people who carry the craft or skill the work requires. | Mandatory | Crafts, Labor qualifications, and the planned labor or crew on the work order or job plan. | Work plan labor craft ELEC, level first-year. Labor ELEC-1 has craft ELEC. | Open the work order plan and the labor record side by side and match craft and skill. | The Gantt shows the work and the resource chart shows nobody qualified. | Add the craft to the labor or crew, or change the plan to a craft you actually have. | Creating work lists in Graphical Work Week |
| Work orders with duration and scheduled dates inside the work-list window | Work with no scheduled dates is left off the Gantt unless Include Work Orders Without Dates is selected. | Mandatory | Work Order Tracking, then the work query on the work list. Start and end dates on the work list. | Three work orders, 4 hours each, scheduled start on a working day inside a two-week list, one finish-to-start predecessor. | Run the work query, then open the Gantt and count the same three records. | The list is empty or the bars sit outside the visible window. | Set scheduled start and finish, widen the work-list dates by a week, or select Include Work Orders Without Dates for undated work. | Creating work lists in Graphical Work Week |
| Site time zone aligned with the work periods | A shift that ends at 15:30 ends at 15:30 on the site clock. A mismatch looks like missing capacity. | Mandatory | Organizations → Sites, time zone. Calendars, work-period hours. | Site time zone Australia/Sydney, work periods written in that clock. | Compare one work period with the site time zone and with the planner’s clock. | Work looks overdue or a person looks unavailable at the start of their shift. | Set the site time zone and regenerate the work periods you will plan against. | Creating work lists in Graphical Work Week |
| Security group for the scheduling application and the work orders | Opening Manage is not the same as opening Graphical Scheduling or changing a schedule. | Mandatory | Manage → Security → Security Groups, and the user type on the suite user | Planner group with Graphical Work Week, Work Order Tracking save, and read on Labor and Crafts. | Sign in as the planner and open the work list. Save a moved bar in a training schedule. | The application is missing from the menu or the save is refused. | Grant the application, the signature options for schedule actions, and site access to the training site. | User access and entitlements in MAS 9.1 and later |
| Optimizer installation, only when a model will run | Resource leveling, capacity planning, maintenance scheduling, labor assignment and spatial scheduling are Optimizer models. | Conditional | Suite administration → Catalog, on the Manage workspace. Optimization scenarios inside Graphical Scheduling or Graphical Assignment. | Leave this empty for a manual Gantt. For a model, confirm Optimizer is deployed before you open the scenario. | Try to run a model only after the Optimizer row in the Optimizer course is in place. | The scenario has no model to run. The manual Gantt is unaffected. | Install Optimizer under its own entitlement, or keep this journey on the manual schedule. | Maximo Optimizer optimization models |
A. Ready to configure
- The proof of entitlement includes Maximo Manage, and the planner’s user type is Base, or Premium if an industry application is also granted.
- AppPoints Usage shows enough available points for that user type. Install points for Optimizer are a separate question.
- The site exists, its time zone is the clock planners will use, and the planner’s security group includes the site.
- One calendar has shifts applied and work periods that run past the first planning window.
- The scheduling application opens and a new work list can be saved.
B. Ready for the first end-to-end journey
- Three training work orders have duration, a craft or crew requirement, and scheduled dates inside the work-list start and end.
- At least one labor or crew record uses that calendar and shift and carries the matching craft or crew type.
- The work query returns those three work orders and no unrelated production work.
- Graphical Resource View shows hours for that person or crew on the working days.
- You can move one bar inside the window, save, and read the new scheduled start back on the work order.
- A work order dated after the work-list end stays off the Gantt, which confirms the window is doing its job.
C. Ready for production operation
- Work periods cover the longest horizon planners will publish, including the extra week Graphical Work Week uses to move work.
- Calendars, shifts, exceptions and non-working periods have an owner and a review before each shutdown or outage window.
- Resource queries are restricted to the crafts and crews that should appear. The default is every person on the calendar.
- Labor and crew time zones and the site time zone have been compared on a shift that crosses midnight.
- If optimization is in scope, the Optimizer course is complete and the model’s objectives are agreed. Scheduler entitlement alone does not cover that install.
- A published schedule has been compared with the work orders after publish, by someone other than the person who built it.
Sources for this readiness check
Licence statements come from the IBM topic named on the row. Installation of a component is a separate check from entitlement.
- Licensing in Maximo Application Suite 9.2 — MAS 9.2 licensing guidance, verified 2026-10-18
- User access and entitlements in MAS 9.1 and later — MAS 9.1 and later, verified 2026-10-18
- Accessing the AppPoints Usage Dashboard — MAS 9.2, verified 2026-10-18
- Creating work lists in Graphical Work Week — Maximo Manage continuous delivery, verified 2026-10-18
- Creating resource lists — Maximo Manage continuous delivery, verified 2026-10-18
- Maximo Optimizer optimization models — Maximo Manage continuous delivery, verified 2026-10-18
Before you start
Planning and scheduling is a Manage capability. Verify installed applications and Optimizer availability separately; do not assume a separate Scheduler add-on is required.
- Planning/scheduling application access.
- Three training work orders, a calendar and known resource availability.
IBM sources + Assetize exercise
01 · Basics — Understand the building blocks
Manage planning and scheduling relates work requirements to available resources and dates. Scheduler capability and an Optimizer solve are distinct activities.
Work duration, resource hours, calendars and dependencies must be interpreted consistently.
Topics in this series
- Work readiness
- Calendars and resources
- Dependencies
- Schedule review
- Optimization handoff
02 · Configuration — Work through the setup
Use a training environment and match the actions to the IBM guide for your installed build.
- Prepare three work orders with durations, required skills and dependencies.
- Create a small schedule using the available scheduling application.
- Inspect the resource calendar and exceptions for the planning window.
- Place the work and examine overlaps, dependencies and unavailable periods.
- Change one availability assumption and review the impact before committing the plan.
03 · Practical example
Fictional teaching example
Two tasks each need four resource hours, but one depends on a delivered part. Eight available hours alone do not make both tasks ready to schedule.
04 · Practice and verify
Create a one-day schedule, then remove half the resource availability and explain the resulting changes.
Expected result
The proposed plan respects readiness, skill, calendar and dependency assumptions.
Common mistakes
- Scheduling work that is not ready.
- Treating effort and elapsed duration as interchangeable.
05 · Advanced concepts
Progress to resource leveling, dispatch and optimization scenarios supported by the deployment. Capture the baseline before publishing changes.
IBM references
Product explanations link to IBM sources. Scenarios and exercises are original Assetize teaching material. Reviewed 2026-10-01.
Maximo ecosystem overview · Manage learning paths · Practice data in Workbench